Today in the morning some of us boys got told to disassemble 4 sheds that had steel framing. We were instructed to separate each house parts form each other so they wont get mixed together when others use it.
Us boys here disassembling the steel wall frames.
Cvui CCS
Monday, 13 June 2011
Trusses Up (13/06/2011)
Today me and the team started to get the trusses up and fix them to the top plates. We ran string lines to line up the middle part of the truss to keep each truss equal.
<--Timber measuring the space between each truss.
<---------string lines--------->
Spacing between each truss was determined by a piece of wood measured at the correct spacing of 845 mm inside both trusses after it was in place we hammered 100mm galvenized size nails to fix them to the top plates.
<--Fixed with 100mm galvanized sized nails to the top plates.
We also used temporary purlins to hold & keep together the trusses, by using scrap pieces of timber left unused.
Tuesday, 7 June 2011
7/06/11
On the site, waiting for our arrival for our roof trusses, eventually came and then we were able to continue with the process of the scaffolds by needing to finish bracing, hand rails, connecting couplers and the last side of the house. We also added kick boards along the inside of the standard poles and created a few stairs to get upto another platform with shorter sized planks.
Eventually we finished our scaffolding on our house and now ready to put up our roof trusses.
Eventually we finished our scaffolding on our house and now ready to put up our roof trusses.
1/06/11
Down at the site today putting up our scaffolding for our unitec house, using poles as ledges, rails braces,temporary and standard posts.We scaffolded the perimeter of our building at about the height were our first nogs are on the wall frames, worked at that height right around the house connecting each pole with coupler connecters.
After break we continued on our process of scaffolding through the day and braced the sides for extra support. we also ran a few ledges along the standards for hand rails for safety.
Put up the planks and had them laid on the metal poles and nailed so they wont move and fall off the poles.
After break we continued on our process of scaffolding through the day and braced the sides for extra support. we also ran a few ledges along the standards for hand rails for safety.
Put up the planks and had them laid on the metal poles and nailed so they wont move and fall off the poles.
Monday, 30 May 2011
30/05/2011
Started today in class working with Rich on our assignment 4543, going over questions in moodle and parts of the calculations. Soon after headed out to the site to finish pluming the corners & sides of the wall frames. We also ran string lines with a dodger block being our length of our top & bottom plate to the string line, the top and bottom plates were then moved to get an accurate position of the walls. We used bracing timber to brace the walls, once it was plum we would hammer a few nails into the brace to the wall till the top & bottom plate was in the correct position. All though we done some good work through the day progressed.
Team Rich
Team Rich
Tuesday, 24 May 2011
Long Day!!
Todays class done great work out on the site, we eventually were able to finish the flooring and get the wall frames up, struggled at first to get in the groove of it but was able to work well with the boys while the day went on.
Tuesday, 17 May 2011
Flooring
3.2.1 Explain using photograph’s, notes and sketches how the flooring was laid on the Unitec house.
You must cover: The type, sizes, direction of sheets, gluing requirements, cutting, nailing patterns, care, lifting, Health and Safety, etc. Include all fixings information as well.
Placing the particle boards, we had to find the full length of the joists and mark the middle. Then came out 800mm from the middle, we had to do this on both right and left sides of the middle mark. This mark is used for string lines to help guide the silver insulation.
Once the joists, and nogs are done. We then needed to use a planner to get the joists all plumb and levelled.
We also created a mechanism to give 100mm slack for insulation, for the floor of the house.
After laying down the insulation we then had to cut out 4 to 3 squares for a place to set the glue for the boards. This was 300mm spacing from each square on each joist.
Eg, of the glue placed into the squares cut out, only problem is that the glue sets within a 10 min period so you have to be quick placing the boards before it sets.
After the glue is placed you then will need to lay your boards 200 mm away from the 800mm, because the size of the boards is 1200 mm wide.so the measurements for the board is 600 mm out from the middle.
To fuse both boards together and getting a tight seal, you will need to glue the sides of board and place them side by side. Use a chisel, and hammer it on the sides to the joists and push the board into the spot where it is getting sealed with glue. Making sure that the board is plumb and equal, you then hammer the boards down with nails.
Subscribe to:
Posts (Atom)